Cestas

Client

Certisolis

ROLE

In situ testing of a PV module

LOCATION

France

DATE

2015

CLIENT SPECIFICS

Sample analysis during construction of the Cestas power plant modules (300MW)

PONTICELLI’S CHALLENGES

  • Analyse 5,000 photovoltaic modules using a mobile test unit, 25 interventions each lasting 2 ½ days.
  • Analysis consisting of: IV curves, measuring of peak power and infrared images on 50% of the modules after preheating to 25°C, electroluminescence and image analysis on 100% of the modules.
  • Setting up of a container to preheat in groups 6 pallets of modules to 25°C before testing

KEY FIGURES

5,000
modules tested


25
interventions each lasting 2 ½ days

Projects

Your Ponticelli contact

Vincent Ladougne

Vincent Ladougne

1 rue Lilienthal - Emerainville - BP 79
77312 Marne-la-Vallée Cedex 2
France
+33 (0)1 64 11 11 64

Contact-us

    For more information about your rights and how to exercise them, particularly the withdrawal of your consent for the use of the information provided in this form, please refer to our privacy policy.